West Main Community Park
Park improvements to include
- 8 individually fenced pickleball courts
- Shade structures
- Seating
- Windscreens
Will this project result in an increase to my property taxes?
- No, the Park District's existing fund balances will be used so there is no need for a referendum or increase to the District's tax levy.
When will the project be completed?
- Construction will begin in early June 2024 and be completed end of July 2024.
Anticipated construction schedule
early June 2024 to end of august 2024
Week of June 17 - Remove old basketball courts
Week of June 24 - Remove old fencing and blacktop
Construction started - Week of June 17
Removal of old basketball nets
CONSTRUCTION - WEEK OF JUNE 24
Removal of old fencing and blacktop